All dam-safety tools
Open breach parameter calculator →

Dam Breach Parameters — Reference

The four regression equation sets used in practice to estimate breach width, side slope, and failure time for embankment dams. All equations below are metric — V in m³, h and B in m, g = 9.81 m/s². Convert before and after; these regressions are not unit-agnostic.

Notation

SymbolMeaningUnits
Average breach widthm
VwReservoir volume at time of failure
VoutVolume of water discharged through breach
hbBreach height (invert to crest)m
hwDepth of water above breach invert at failurem
VerVolume of embankment material eroded
KoFailure-mode factor (overtopping vs piping)
tfBreach formation (failure) times or hr

The Four Equation Sets

Froehlich (2008) — current default

B̄ = 0.27 · Ko · Vw0.32 · hb0.04
tf = 63.2 · √[ Vw / (g · hb²) ]   (seconds)

Ko = 1.3 overtopping, 1.0 piping. Side slope 1.0H:1V overtopping, 0.7H:1V piping. Based on 74 case histories — the largest dataset of the four, and the reason this set is the usual starting point.

Froehlich (1995)

B̄ = 0.1803 · Ko · Vw0.32 · hb0.19
tf = 0.00254 · Vw0.53 · hb−0.90   (hours)

Ko = 1.4 overtopping, 1.0 piping. Side slope 1.4H:1V overtopping, 0.9H:1V piping. Superseded by the 2008 set but still cited and still offered in most software.

MacDonald & Langridge-Monopolis (1984)

Ver = 0.0261 · (Vout · hw)0.769   (earthfill)
tf = 0.0179 · Ver0.364   (hours)

Predicts eroded volume rather than width directly — breach geometry is then back-figured from the embankment section, assuming a trapezoid with 0.5H:1V side slopes. The distinct approach is exactly why it is a useful independent check.

Von Thun & Gillette (1990)

B̄ = 2.5 · hw + Cb
tf = 0.02 · hw + 0.25   (erosion-resistant, hours)
tf = 0.015 · hw   (easily erodible, hours)

The only set that keys failure time to erodibility rather than volume alone, which makes it the useful bracket when embankment materials are known.

Failure-Mode Factor Ko and Side Slopes

MethodKo overtoppingKo pipingSide slope z (H:1V)
Froehlich (2008)1.31.01.0 OT / 0.7 piping
Froehlich (1995)1.41.01.4 OT / 0.9 piping
MacDonald & L-M0.5 (assumed)
Von Thun & Gillette1.0 typical

Von Thun & Gillette Offset Cb

Reservoir volume Vw (m³)Vw (ac-ft)Cb (m)Cb (ft)
< 1.23×106< 1,0006.120
1.23×106 – 6.17×1061,000 – 5,00018.360
6.17×106 – 1.23×1075,000 – 10,00042.7140
> 1.23×107> 10,00054.9180

Worked Comparison — All Four Methods

Small high-hazard embankment, overtopping failure. Vw = 500 ac-ft (616,800 m³), hb = hw = 30 ft (9.14 m), earthfill.

MethodB̄ (m)B̄ (ft)tf (hr)
Froehlich (2008)27.3900.48
Froehlich (1995)27.4900.41
Von Thun & Gillette29.0950.43 resistant / 0.14 erodible
MacDonald & L-MVer = 4,060 m³0.37

Breach widths cluster within about 6% here, but failure time spans 0.14 to 0.48 hours — a factor of 3.4. That spread is the whole point of running more than one method.

Failure time drives peak outflow, not breach width. Peak breach discharge is far more sensitive to tf than to B̄, so the parameter with the widest prediction band is also the one the answer hinges on. Froehlich (2008) reports roughly ±⅓ uncertainty on width and closer to a factor of two on time. Run the range, not a single deterministic number, and state the range in the report.

Practice Notes

IssueGuidance
Which method to lead withFroehlich (2008) — largest dataset, HEC-RAS default for embankments
Concrete gravity / arch damsThese regressions do not apply. Use monolith-loss assumptions per FERC / USACE guidance
Very small damsCase-history datasets thin out below about 6 m height; treat results as indicative
Regulatory submittalsMost state programs expect a sensitivity range across at least two methods
Vw definitionVolume at the moment of failure, not normal pool — for an overtopping case that is the routed peak

Sources: Froehlich, D.C. (2008), "Embankment Dam Breach Parameters and Their Uncertainties," J. Hydraulic Engineering 134(12), 1708–1721. Froehlich, D.C. (1995), "Embankment Dam Breach Parameters Revisited," ASCE Water Resources Engineering, 887–891. MacDonald, T.C. & Langridge-Monopolis, J. (1984), "Breaching Characteristics of Dam Failures," J. Hydraulic Engineering 110(5), 567–586. Von Thun, J.L. & Gillette, D.R. (1990), "Guidance on Breach Parameters," USBR. See also USACE HEC-RAS Hydraulic Reference Manual (dam breach chapter) and FERC Engineering Guidelines Chapter 2. Comparison values above were computed directly from the equations as written.

Running the numbers? Open the breach parameter calculator → · Routing the hydrograph? Dam breach outflow · All dam-safety tools.

Related cheat sheets and tools

Breach geometry from this card feeds the dam breach outflow and reservoir routing tools. Hazard class drives whether a breach study is required at all — see hazard classification and inflow design flood. For the erosion side of an overtopping failure, see embankment seepage and exit gradient.

Get future cheat sheets in your inbox

One reference card or worked-example case study per month, delivered the moment it's published. Free.

Free. Unsubscribe anytime. Privacy.