90° V-Notch Weir — Seepage Monitoring Worked Example
Rating the 90° V-notch weir at a dam's toe-drain outfall — the standard low-flow measurement structure in dam-safety monitoring, because the triangular section keeps sensitivity high when the flow is a trickle. We derive the working rating, build the head-discharge table for the inspection log, and cover the installation rules that make a staff-gage reading defensible. Sources: USBR Water Measurement Manual; Kindsvater & Carter / Kindsvater-Shen weir research (USGS); ASTM D5242.
The structure
| Weir | 90° V-notch, sharp-crested steel plate in the toe-drain outfall channel |
| Purpose | Weekly seepage reading + comparison against historical baseline |
| Observed head today, H | 0.35 ft above the notch vertex (staff gage) |
| Discharge coefficient Cd | 0.58 (fully contracted sharp notch; see weir C card) |
From the general triangular-weir form
For θ = 90°: tan(45°) = 1, √(2g) = 8.025 ft1/2/s
Q = 0.58 · 0.533 · 8.025 · H2.5 = 2.48 · H2.5 [Q cfs, H ft]
The precise Kindsvater-Shen treatment adds a small head correction k (≈ 0.003 ft for 90°) and lets Cd vary slightly with geometry; for monitoring purposes the constant-coefficient form above is the standard field rating.
H = 0.35 ft
Q = 2.48 · 0.0725 = 0.180 cfs = 81 gpm
Q = 2.48·H2.5
| Head H (ft) | Q (cfs) | Q (gpm) |
|---|---|---|
| 0.20 | 0.044 | 20 |
| 0.35 | 0.180 | 81 |
| 0.50 | 0.438 | 197 |
| 0.75 | 1.21 | 542 |
| 1.00 | 2.48 | 1,113 |
Note the 5/2-power leverage: a tape-measure error of 0.05 ft at H = 0.35 moves the reported flow by roughly +40% / −32%. Read the gage carefully, and keep H above about 0.2 ft for accuracy — below that, nappe clinging and surface tension degrade the rating (a reason the notch angle, not a rectangular weir, is used for trickle flows in the first place).
Why some monitoring weirs lie
- Measure H upstream, not at the notch. The water surface drops as it accelerates into the notch; gage at least 4×Hmax upstream of the plate.
- Ventilated, free-falling nappe. The jet must spring clear of the plate with air behind it; a drowned or clinging nappe reads high. Keep tailwater well below the vertex.
- Full contractions. The approach pool should be wide and deep relative to the notch so flow contracts fully; Cd = 0.58 assumes it.
- Sharp, clean edge. A chamfered upstream edge (≤ ~2 mm crest thickness), free of rust bloom, algae, and debris — cleaning the notch is part of the reading.
- Still approach. Baffle or still the approach pool; surging makes the staff gage unreadable at exactly the low heads where the V-notch earns its keep.
Tools used in this example
Reproduce every step: V-notch weir tool with Cd from the weir coefficient card. For the seepage quantity the weir is measuring, see embankment seepage and the exit gradient check, with hydraulic conductivity ranges from the soil permeability card; for the broader monitoring program, the dam-safety tool set.