Dam safety worked examples

Class B or Class C? Working the 1.5-Foot Flood Rise Test

By Michael Flynn, PE · water resources & dam safety engineer

The difference between an intermediate-hazard and a high-hazard dam in North Carolina comes down to a single measured quantity, and the rule leaves almost no judgment in it. This is that determination worked against surveyed elevations — including the part practitioners get wrong most often, which is which elevation the 1.5 feet is measured above.

The situation

Dam22-ft earthfill, 145 ac-ft, recreation impoundment
Breach modelFroehlich 2008 / 1995 — B̄ = 59.4 ft, tf = 0.39 hr, Qp = 7,150 cfs
Structure of concernOne occupied single-family dwelling, ~2,400 ft downstream
PositionOn a terrace off the main valley, outside the direct breach path
Lowest adjacent grade (surveyed)812.4 ft
Lowest floor elevation (surveyed)813.1 ft
Modeled peak breach WSE at the structure813.6 ft
Step 1 · What the rule actually says

15A NCAC 02K .0105(a)(2)

Class B covers dams whose failure "may damage highways or secondary railroads, cause interruption of use or service of public utilities, cause minor damage to isolated homes, or cause minor damage to commercial and industrial buildings." Everything turns on minor, which the rule then defines with no wiggle room. Damage is minor only when the structures are:

And then it closes: "All other damage potential will be considered serious."

Step 2 · Pick the governing elevation

The lower of the two — this is the common error

Lowest adjacent grade outside foundation walls = 812.4 ft
Lowest floor elevation             = 813.1 ft

Governing elevation = min(812.4, 813.1) = 812.4 ft  (adjacent grade)
Do not default to the finished floor. The rule says the lower of the two governs, and for a slab-on-grade or crawlspace dwelling on sloping ground the adjacent grade is almost always lower. Measuring rise above the floor instead of the grade understates it — here by 0.7 ft, which is nearly half the entire 1.5-ft allowance. That single substitution has turned Class C dams into Class B on paper.
Step 3 · Compute the rise

Peak breach WSE minus the governing elevation

Flood rise = 813.6 − 812.4 = 1.2 ft

1.2 ft ≤ 1.5 ft  →  damage is minor on the rise test
Structure is outside the direct breach path  →  backwater test also satisfied
Both conditions are met, so this structure supports a Class B classification — assuming nothing else downstream fails either test, and subject to the Director's approval under .0105(b).
Step 4 · How little it takes to flip

The same dam at a slightly higher stage

Re-run the breach with a modestly larger volume, a lower breach invert, or simply a less favourable roughness assumption downstream, and the peak WSE at the structure comes in at 814.1 ft instead:

Flood rise = 814.1 − 812.4 = 1.7 ft

1.7 ft > 1.5 ft  →  damage is serious
Class C, high hazard
Modeled WSERise above 812.4TestClassConsequences
813.6 ft1.2 ftMinorBEAP required
814.1 ft1.7 ftSeriousCEAP required + PMF spillway

Half a foot of modeled stage — well inside the uncertainty of any breach regression — moves the dam between classes. In North Carolina both classes require an emergency action plan, so the EAP obligation does not turn on this. What does turn on it is the inflow design flood, which jumps from a 100-year-to-½-PMF range at Class B to the full PMF at Class C.

Step 5 · The tests you can still fail

Passing 1.5 ft is necessary, not sufficient

Tools used

Hazard Classification
Screen the consequence criteria
Dam Breach Peak Discharge
The hydrograph behind the stage
NC Class A/B/C Rule →
Full 15A NCAC 02K .0105 text

The rest of this series

These four examples follow one structure through the whole decision chain, because in practice that is how the questions actually arrive:

  1. Breach parameters for a 22-ft earthfill dam — produces the failure hydrograph everything else depends on.
  2. Class B or Class C? The 1.5-foot flood rise test — turns that hydrograph into a hazard classification.
  3. Does an 18-ft farm pond dam need a permit? — the classification decides whether the size exemption survives.
  4. Spillway design flood for a Class C dam — and the classification sets the storm the spillway must pass.

Scope. This page is general information about North Carolina dam safety regulation, current as of 2026-08-28. It is not an engineering opinion about any specific structure and it is not legal advice. Requirements change when the General Assembly amends the Dam Safety Law or the Environmental Management Commission amends the rules — always confirm against the current text of the statute and 15A NCAC 02K, and contact the NCDEQ Dam Safety Program for a determination that binds.

Monthly engineering case studies

One real stormwater, dam, or hydraulics design problem per month, with the math worked out and the gotchas called out. No tutorials, no fluff.

Free. Unsubscribe anytime. Privacy.